The construction for the 4,800-square-foot Multimedia Arts Program (MAP) building located behind woodshop and the weight room began early September and is making progress. The $2.2 million project's most current milestone has been the completion of the electrical work.
"We had a few hiccups," said media arts teacher Tony Palma. "In the process of the work, the equipment failed and there were some expenses in fixing that."
This first problem arose when the construction workers re-routed the primary PG&E electrical line for the MAP building.